Northern Virginia Stream Restoration Bank

Home -- Timeline


2002

March 2002

Reston Watershed Plan published (identifies need to improve watershed)



2003

October 2003

Letter of Intent signed with Reston

Mitigation Banking Review Team (MBRT) Meeting requested


December 2003

MOA signed

$250,000 Donation for Reston Nature House



2004

January 2004

Meetings with the Mitigation Banking Review Team began


June 2004

Public Notice for Prospectus for the Northern Virginia Stream Restoration Bank (NVRSB)


October 2004

First of 5 MBI drafts submitted to agencies



2005

Febuary 2005

Installed 9 water level gauges in the Snakeden watershed to confirm flow rates

Installed rain gauge just above the Snakeden watershed boundary to measure rainfall


March 2005

HB 2464 is signed by the Governor


July 2005

HB 2464 goes into effect, allowing natural channel designs to overtop more frequently than concrete or rip-rap channels



2006

February 2006

DEQ & COE sign 5th MBI draft! - Bank limited to Phase I (14 miles)


June 2006

Concept Plan Approved by DEQ & COE on June 2, 2006


November 2006

Installed 4 water level gauges in the Glade watershed to confirm flow rates

Installed 5 water level gauges in the Colvin Run watershed to confirm flow rates



2007

March 2007

Installed additional rain gauges (one near the downstream end of the Glade and Snakeden watersheds and one in the Colvin Run watershed) to measure rainfall


September 2007

Reach 2 of the Snakeden Watershed approved by the Reston Design Review Board


December 2007

Submitted plans for Reaches 3 through 8 of the Snakeden Watershed to the Reston Design Review Board

Reaches 3 through 8 of the Snakeden Watershed approved by Reston Design Review Board

Began preliminary plans for the Glade Watershed

Pre-bid meeting for Reaches 1 and 2



2008

January 2008

Reaches 9-11 of the Snakeden Watershed approved by Reston Design Review Board

VDOT permit approved for Reaches 1-3 of the Snakeden Watershed

Began design of Reach 1 of the Glade Watershed


February 2008

Began design of Reaches 2 and 3 of the Glade Watershed

Ground-breaking ceremony for Reaches 1-3 of the Snakeden Watershed

Construction commenced!


April 2008

Completed construction of Reaches 1, 2, and 3 of the Snakeden Watershed

Began construction of Reach 4 of the Snakeden Watershed


June 2008

The NVSRB was awarded a Resolution by Fairfax County to congratulate the project's success

Completed construction of Reach 4 upstream of Glade Drive in the Snakeden Watershed


September 2008

September 6 - Tropical Storm Hanna drops over 6" of rain in 9 hours, and the restored streams respond beautifully


October 2008

NVSRB is a finalist in the Washington Business Journal's Green Business awards program


December 2008

December 2 - Informational meeting for the Glade watershed

December 4 - NVSRB awarded a 2008 Fairfax County Land Conservation Award for protecting natural resources

December 13 - Two citizen stream walks (approximately 150 people in attendance) of completed Snakeden construction

December 16 - Reston Design Review Board hearing for the Glade Reaches 1, 2, and 3



2009

January 2009

January 10 and 17 - Informational plan reviews and stream walks for the Glade Reaches 1, 2, and 3 (approximately 120 citizens in attendance)

January 27 - The Glade Reaches 1, 2, and 3 approved by the Design Review Board


February 2009

February 5, 6, and 7 - Plant rescue in The Glade Reaches 1, 1A, 2, and 3

February 18 - Tree removal begins for The Glade Reaches 1, 1A, 2, and 3


March 2009

March 7 and 28 - Informational plan reviews and stream walks for the Glade Reach 4

Construction is complete in the Snakeden watershed!

Construction begins in The Glade Reach 1


April 2009

April 21 - Reston Design Review Board Preliminary Plan review for Reach 4


May 2009

May 9 and 30 - Informational plan reviews and stream walks for the Glade Reach 4

Construction is complete in The Glade Reach 1

Construction begins in The Glade Reaches 2 and 3


June 2009

June 16 - Reston Design Review Board final review of The Glade Reach 4

June 27 - Informational plan review and stream walk for the Glade Reaches 5 and 6


July 2009

July 25 - Informational plan review and stream walk for the Glade Reaches 5 and 6


August 2009

August 18 - Reston Design Review Board preliminary plan review of The Glade Reaches 5 and 6



Looking Ahead

2009/2010


Please click here for a schedule of upcoming events related to the restoration of The Glade Reaches 5 and 6