Timeline Progress
Initial Watershed Study and Survey: COMPLETE
Phase I Archeological Investigation: COMPLETE
Concept Design: COMPLETE
Final Plan: COMPLETE
MBRT Approval: APPROVED
Reston Design Review Board Approval: APPROVED April 29, 2008
County Approval: APPROVED May 29, 2008
VDOT Approval: APPROVED
Construction: COMPLETE
Plan views: AVAILABLE [.pdf file; 5.5 MB]
|