Reach 3

The Glade Watershed


Glade Reaches 2 and 3

Timeline Progress

Initial Watershed Study and Survey: COMPLETE

Phase I Archeological Investigation: COMPLETE

Concept Design: COMPLETE

Plan Design: COMPLETE

MBRT Approval: APPROVED

Reston Design Review Board Approval: APPROVED

County Approval: APPROVED

Construction: Tree removal completed in February 2009; construction begun May 2009; expected completion October 2009. (Based on weather, planting activities may continue outside this window.)


Plan views: The following plan sets have been updated to reflect resident concerns from the December 2, 2008 meeting.

The following sheets (2-8 of 82) are the grading plan sheets as excerpted from the overall plan set:

Plan Set Sheet 2 (Overall grading plan) [.pdf 965KB]

Plan Set Sheet 3 (Individual grading plan sheet) [.pdf 1.1MB]

Plan Set Sheet 4 (Individual grading plan sheet) [.pdf 1.1MB]

Plan Set Sheet 5 (Individual grading plan sheet) [.pdf 1.1MB]

Plan Set Sheet 6 (Individual grading plan sheet) [.pdf 1.2MB]

Plan Set Sheet 7 (Individual grading plan sheet) [.pdf 1.1MB]

Plan Set Sheet 8 (Individual grading plan sheet and plan legend) [.pdf 1.0MB]

All Grading Plan Sheets (sheets 2-8 above.) [.pdf 7.6MB]


Tree Save Plan Sheet 1 [.pdf 858KB]

Tree Save Plan Sheet 2 [.pdf 769KB]

Tree Save Plan Sheet 3 [.pdf 772KB]

Tree Save Plan Sheet 4 [.pdf 847KB]

Tree Save Plan Sheet 5 [.pdf 897KB]

Tree Save Plan Sheet 6 [.pdf 754KB]

Tree Save Plan Sheet 7 [.pdf 705KB]

Full Tree Save Plan (sheets 1-7 above.) [.pdf 5.6MB]

Tree List and Summary [.pdf 102KB]


Overall Stationing Map for the Glade, Reaches 1, 2, and 3 [.pdf 362KB]

Wildlife Habitat Assessment for the Glade, Reach 3 [.pdf 5.8MB]

Endangered and Threatened Species Assessment for the Glade, Reach 3 [.pdf 9.3MB]




Pre-Construction Photos

Construction Photos

Post-Construction Photos











First-Year Monitoring Photos